Agile Real Estate Development

1 building on Homelore · Mont Kiara · completed 2019

A subsidiary of Agile Property Holdings Limited

Also known as Agile Real Estate Development (Agile Group-PJD JV), Agile Group-PJD JV

What we found

Mixed-to-negative: residents report construction/workmanship defects (drainage leaks, shaky lifts, thin walls) and an expat court win against the developer over quality;

The evidence

10 claims across 5 areas

Delivery

Negative
  • The same judgment found only a slight delay in delivery of vacant possession of the unit and allowed liquidated ascertained damages for 28 days (1 December 2020 to 29 December 2020) at RM729.53 per day, rejecting the plaintiffs' wider delay case.

Defects and workmanship

Negative
  • In a written judgment of the High Court of Malaya at Kuala Lumpur (Construction Court 1), Writ WA-22C-10-01/2022, Nadzarin Wok Nordin J found that a purchased unit at the Agile Mont Kiara project had numerous defects including dampness, water leaks, water ingress, a failed waterproofing system, wall cracks, flooring issues and incomplete finishing that had not been properly remedied, rendering the parcel uninhabitable, and held that the developer Agile PJD Development Sdn Bhd had failed in its implied obligation to construct the parcel to a standard befitting a luxury condominium.

One more finding
  • The workmanship complaints are persistent and real: leaks, thin walls, lift trouble, and the expat owners took the developer to court and won.

    Agile Mont Kiara

Post-handover response

Mixed
  • At Residensi Duta Kiara (formerly Agile Mont Kiara), where keys were handed over in 2020 and the defect liability period ended in July 2023, the developer has returned to carry out further works including in the car park area and additional layering to the basketball court surface; the criticism of standards is directed at a previous management company rather than the developer.

One more finding
  • In the same judgment the court concluded that Agile PJD Development Sdn Bhd had negligently failed to carry out defect rectification works properly and diligently, found delays in addressing defects that were without valid justification and that aggravated the damage, awarded RM189,538.15 special damages, RM200,000 general damages and RM100,000 exemplary damages (the court describing the defendant's conduct as lackadaisical), and ordered the developer to issue within 14 days a letter of guarantee and indemnity to rectify the defects within not more than six months.

Regulatory and legal

Negative
  • The workmanship complaints are persistent and real: leaks, thin walls, lift trouble, and the expat owners took the developer to court and won.

    Agile Mont Kiara

Corporate continuity

Negative
  • Agile Group Holdings, the Hong Kong-listed Guangzhou-based developer, failed to service the coupon on a US$483 million bond maturing in 2025 within a grace period that ended on 13 May 2024 and said it would not be able to fulfil all payment obligations under its offshore debts; this does not mention Malaysia, and no source retrieved in this session ties this default to the Malaysian entity Agile Real Estate Development (M) Sdn Bhd or to the project company Agile PJD Development Sdn Bhd.

3 more findings
  • Agile Property Holdings Limited, through its local subsidiary Agile Real Estate Development (M) Sdn Bhd, developed Agile Mont Kiara in a joint venture with PJ Development Holdings Bhd, reported at the project's 2015 groundbreaking ceremony.

  • At the project's official launch, Agile Mont'Kiara was reported as a joint venture between Agile Real Estate Development Sdn Bhd and PJ Development Holdings Bhd, the first international project of Hong Kong-listed parent Agile Property Holdings Ltd, with a gross development value of RM1.4 billion across 11 towers and 813 units.

  • PJ Development Holdings Berhad's 2024 audited financial statements record that its wholly-owned subsidiary PJD Hartamas Sdn Bhd disposed of its entire equity interest in Agile PJD Development Sdn Bhd, a 30% associate, on 9 September 2024 for a total consideration of RM3, after the associate had paid PJD dividends of RM4.5 million, RM4.5 million and RM2.1 million during 2023.

Their buildings